The coverage structure: 1-2-10
Most production builders — directly or through a third-party warranty company — structure coverage in three tiers:
| Period | What it typically covers |
|---|---|
| Year 1 | Workmanship and materials: fit, finish, and function of the home as delivered — doors, drywall, paint, flooring, fixtures, and defects in how things were built or installed. |
| Years 1–2 | Major systems: plumbing, electrical, and heating/cooling delivery systems inside the walls. |
| Years 1–10 | Structural components: load-bearing elements — foundation, framing, roof structure — against actual structural failure or major defect, as defined in the warranty document. |
The usual exclusions matter as much as the coverage: normal wear and tear, normal house settling within accepted trade practices, damage caused by the owner or third parties, appliances and equipment covered by their own manufacturer warranties, and anything you or your contractors altered after closing. Your specific warranty booklet — not the sales brochure — is the contract. Read its definitions before you need them.
Florida's floor: the mandatory 1-year warranty (§553.837)
Since July 1, 2025, Florida law sets a minimum no builder can go below. Under §553.837, Florida Statutes, a builder must warrant a newly constructed home (single-family, duplex, triplex, or quadruplex that has not been previously occupied) for 1 year against construction defects in equipment, material, or workmanship — including work by subcontractors and suppliers — that result in a material violation of the Florida Building Code.
The statute fixes the start of that year in its own words: the warranty runs “for a period of 1 year after the date of original conveyance of title to the initial owner or after the date of initial occupancy of the dwelling, whichever occurs first” (§553.837(2), Florida Statutes).
- The year runs from the earlier of the date title is conveyed to the initial owner or the date the home is first occupied.
- The builder must remedy covered defects at the builder's expense and restore any work damaged in making the repair.
- The obligation lasts the full year even if the home is sold or transferred — the warranty follows the home to the new owner during year one.
- A builder may satisfy the requirement with its own express written warranty, provided it meets the statute's conditions and discloses its terms.
Note the limit honestly: the statutory warranty reaches defects that amount to a material building-code violation. Ordinary cosmetic items live in the builder's own year-1 workmanship coverage — which is exactly why the 11-month process below matters.
Everything above that floor lives in the builder's own written warranty, not the statute. Cosmetic and workmanship coverage, the year-two systems tier, and structural coverage out to year ten exist only on the terms that document sets — check your builder's written warranty for its cosmetic, systems, and structural coverage before you count on any of it.
For the law itself — how HB 623 created this warranty, what it excludes, and when a builder's express written warranty can supersede it — see the companion guide: Florida's HB 623 builder warranty, explained.
How to file a claim — step by step
- Document it first. Dated photos and video of the defect, plus when you first noticed it. Documentation made today beats memory in month ten.
- Submit in writing, through the builder's official channel. Most builders run warranty portals — use it, and keep the confirmation. A phone call starts nothing; a written submission with a timestamp starts the clock.
- Reference the coverage tier. Say which tier you are claiming under (year-1 workmanship, systems, structural, or the §553.837 statutory warranty) and describe the defect and its location precisely enough for the builder to find it without hunting.
- Log every response. Dates of inspections, what the trade said, what was promised, and by when. If it isn't in writing, it didn't happen.
- Verify the repair, then close the loop in writing. Photograph the finished work and confirm acceptance — or non-acceptance — in the same portal thread.
Timing windows that decide outcomes
- Water intrusion and safety issues: same day. Active leaks, electrical hazards, and anything that can cascade into bigger damage gets reported immediately — and mitigated (shut the water off) before you document. Waiting turns a covered defect into an argument about consequential damage.
- Cosmetic items: batch them. Paint, drywall, caulk, and minor fit-and-finish items are handled most efficiently as a list at the builder's 30–60-day review and again at the 11-month review. Builders schedule these windows; use both.
- The 11-month inspection: the single highest-value appointment of year one. Hire an independent inspector who does new construction, about 30 days before your first anniversary. Their report becomes your documented, in-warranty claim list while the full year-1 coverage is still alive. Our free checklist below is built for exactly this walk-through.
If the builder won't fix it: escalation, and Florida's Chapter 558
Escalate in writing, in order: warranty portal supervisor → builder's division warranty manager → corporate customer care — each step in writing, each with your documentation attached. If a construction-defect dispute still isn't resolved, Florida law imposes a pre-suit process before you can file an action: Chapter 558, Florida Statutes (§558.004).
- Written notice of claim served at least 60 days before filing an action (120 days for an association representing more than 20 parcels). The notice must refer to Chapter 558 and describe each defect in reasonable detail, with its location.
- Inspection: the builder is entitled to inspect the property within 30 days after service of the notice (50 days for large associations), and you must provide reasonable access.
- Written response: within 45 days after service (75 days for large associations), the builder must respond in writing — offering to repair at no cost, offering a monetary settlement, offering a combination, or stating that it disputes the claim.
- Your decision window: if you receive a settlement offer, you generally have 45 days to accept or reject it in writing.
- One trap: a Chapter 558 notice does not stop the statute-of-repose clock (below). Do not let a slow negotiation run past a deadline.
The deadlines behind everything (§95.11)
Two clocks govern construction-defect claims in Florida. The statute of limitations is generally 4 years — for hidden (latent) defects, 4 years from when the defect was discovered, or should have been discovered with due diligence. The statute of repose is an absolute outer bar: 7 years from the earliest of the issuance of a temporary certificate of occupancy, the certificate of occupancy, a certificate of completion, or abandonment of construction. (SB 360 (ch. 2023-22, Laws of Florida) shortened the repose period from 10 years to 7 in 2023.) Once the repose date passes, a claim is generally barred — even for a defect nobody could have seen. This is the practical reason the 11-month inspection matters: find it early, while every remedy is still open.
Practical tips from the buyer's side of the table
- Keep one warranty file: the warranty booklet, your contract, every punch list, the certificate of occupancy, and your claim confirmations — together, from closing day.
- Check the arbitration clause early. Many builder contracts include one; know whether it is there before a dispute, not during one.
- Get trade-offs in writing before you sign. Warranty response timelines and preferred-lender terms belong in your contract file — this is part of how Oday structures a purchase, detailed on the builders hub.
- Talk to recent owners in the specific community about how warranty service actually went — before you buy, while you can still choose.
- Hire your own inspector — one who specializes in new construction — at pre-drywall (if you build from dirt), before closing, and again at month 11.
Free: the 11-Month Warranty Inspection Checklist
The exact walk-through list Oday's buyers use before the first anniversary — every room and system from this guide, in the order an inspector works. Enter your details and it appears right here; we'll also note your home's anniversary window so the timing doesn't slip.
The 11-Month Warranty Inspection Checklist
Work it room by room with dated photos. Anything you find goes to the builder in writing, through the warranty portal, before the anniversary date.
- ☐ Exterior & structure: foundation cracks beyond hairline settling; stucco/siding cracks and separation; roof — missing or lifted shingles/tiles, flashing at every penetration; soffit and fascia gaps (pest entry).
- ☐ Water management: grading sloping away from the foundation; gutter and downspout discharge; lanai and patio drainage; hose bibs and exterior faucets for leaks.
- ☐ Windows & doors: every window opens, closes, and locks; seals intact (no fogging between panes); door alignment and weatherstripping; sliding doors roll and latch.
- ☐ Plumbing: under every sink — supply lines, traps, shut-offs — for moisture; toilet bases and water lines; water heater pan and T&P line; tub/shower caulk and grout integrity; water pressure and drainage speed throughout.
- ☐ HVAC: cooling and heating both run; temperature split across rooms; condensate drain line clear; filter size and condition; thermostat programs hold.
- ☐ Electrical: every GFCI tests and resets (kitchen, baths, garage, exterior); panel labeled and breakers seated; ceiling fans wobble-free; all outlets and switches live.
- ☐ Interior finishes: drywall cracks and nail pops (mark settling vs. defect); paint and caulk separation at trim and counters; flooring — hollow tiles, lifting planks, carpet seams; cabinet doors/drawers aligned and soft-close working.
- ☐ Kitchen & appliances: every appliance runs a full cycle; range hood vents outside; garbage disposal and dishwasher drain without leaks; refrigerator water line dry behind the unit.
- ☐ Garage & attic: door opener safety reverse works; attic insulation even and undisturbed; no daylight at roof penetrations; attic access sealed.
- ☐ Safety: smoke and CO detectors test; pool barrier/alarms if equipped; handrails secure.
- ☐ The paper: assemble warranty booklet, contract, punch lists, CO, and every claim confirmation in one file; photograph the full set; submit the claim list in writing through the builder's portal — before the anniversary.
Want a professional set of eyes instead? Call Oday at 941-948-4284 — he'll refer inspectors who do new construction and help you work the claim list with the builder.
Buying new construction now?
The warranty is only half the protection — the other half is how the purchase is structured before you sign. Oday registers you before your first visit, documents every walk-through, and gets the trade-offs in writing. Call or text 941-948-4284, and compare live builder offers in the Builder Deal Finder.
New-construction warranty questions, answered
What does a new-construction warranty cover in Florida?
Most builders provide a 1-2-10 structure: workmanship and materials for year 1, major systems (plumbing, electrical, HVAC) for years 1–2, and structural components for years 1–10. On top of that, Florida law (§553.837, Florida Statutes, effective July 1, 2025) requires every builder of a newly constructed home to warrant it for 1 year against construction defects in equipment, materials, or workmanship that amount to a material violation of the Florida Building Code — and the builder must remedy covered defects at the builder's expense. The year runs from the earlier of the original conveyance of title to the initial owner or the home's initial occupancy, whichever comes first.
Is the Florida builder warranty transferable if I sell the home?
Yes, for the first year. Under §553.837, the builder must honor the warranty for the full 1-year period even if the home is sold or transferred and is no longer owned by the initial owner. Longer structural coverage under a builder's or third-party warranty program may also transfer — check the specific warranty documents.
When should I get an 11-month warranty inspection?
About 30 days before your first anniversary of ownership. Most cosmetic and workmanship items are covered only in year 1, so a professional new-construction inspection at month 11 — while the full warranty is still in force — turns the findings into a documented, in-warranty claim list instead of your repair bill in year 2.
What is Chapter 558 and do I have to follow it before suing a builder in Florida?
Chapter 558, Florida Statutes, is the mandatory pre-suit process for construction-defect claims. Before filing an action, the claimant must serve a written notice of claim at least 60 days in advance (120 days for associations representing more than 20 parcels). The builder may inspect within 30 days of the notice and must serve a written response within 45 days (75 days for large associations) — offering repairs, a monetary settlement, both, or disputing the claim. Skipping this process can stall or sink an otherwise valid claim.
How long do I have to bring a construction-defect claim in Florida?
Generally, an action must be brought within 4 years — for hidden (latent) defects, 4 years from when the defect was discovered or should have been discovered. There is also an absolute outer deadline, the statute of repose: 7 years from the earliest of the temporary certificate of occupancy, certificate of occupancy, certificate of completion, or abandonment of construction (§95.11(3)(b), Florida Statutes, as shortened by SB 360 (ch. 2023-22, Laws of Florida) in 2023). After the repose date, a claim is generally barred even if the defect was undiscoverable. This is general information, not legal advice.
Sources (checked November 23, 2026): §553.837, Florida Statutes, created by HB 623 (ch. 2024-95, Laws of Florida); §558.004, Florida Statutes (Chapter 558 notice and opportunity to repair); §95.11(3)(b), Florida Statutes, as amended by SB 360 (ch. 2023-22, Laws of Florida, 2023). This page is general information about how warranties and claims work — it is not legal advice, and your own warranty documents and contract control your specific rights.